All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Brenham ISD
IFCB Posted : Dec 2, 2022
Bid Deadline : Friday, Jan 20, 2023

Questions Due By : Tuesday, Dec 20, 2022
Applicant Address : Brenham, TX 77834
IFCB ID : 230006905

IFCB Requirements :

·        All Questions and Bids must be submitted using the on-line IFCB system. If for some reason the system is down before the respective deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission.

 

·        Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·        Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·        By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·        Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·        Contracts must not prohibit SPIN changes.

 

·        Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·        Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·        All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·        All contracts awarded under this IFCB bidding process may be voluntarily renewed by the applicant, upon written notice to the provider, for five consecutive one year terms. Please include this language in your final contract.

 

·        All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·        If the applicant is requesting purchases of new equipment, or maintenance of that new equipment, bids for functionally equivalent equipment will be accepted.

·        E-rate rules require applicants to evaluate the cost of eligible goods and services, and to cost-allocate out the amount for ineligible services from their funding request. If your company will be bidding internet access service, please identify the amount to be cost-allocated out for the ineligible services – email service, web hosting, content filtering, or other bundled ineligible services.

·        INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

·        INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

 

·        The winning vendor will be required to complete the USAC approved Item 21 template for the project within 7 working days after notification that the vendor has won the bid.

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT B: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

·        DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components of a single project will be disqualified.


Services and Equipment Requested :

UPDATE 12.23.22 - THE BID DEADLINE HAS BEEN UPDATED TO 1.20.23.

UPDATE 12.19.22 - Vendor QA from the 12.19.22 walkthrough is now available for download along with this IFCB.

UPDATE: A second 470/IFCB # 230009421 has been posted for the racks (fiber enclosures) that were originally included in the statement of work available for download. Also, under IC Project B, 23 stacking cables were included. 

Category One:

Internet Access – the district currently has 2.4GB internet access and would like to increase their bandwidth. The terminating address for this circuit is located at 1301 Niebuhr, Brenham, TX 77833. Vendors should bid 2 GB through 4 GB.  Bids should be based on a 3-year term.

 

E-rate rules require applicants to evaluate the cost of eligible goods and services, and to cost-allocate out the amount for ineligible services from their funding request. If your company will be bidding internet access service, please identify the amount to be cost-allocated out for the ineligible services – email service, web hosting, content filtering, or other bundled ineligible services.

INTERNET ACCESS DISQUALIFICATION FACTOR: Bids submitted for services to an incorrect address will be disqualified.

 

INTERNET ACCESS DISQUALIFICATION FACTOR: Any and all installation charges must be identified on your bid. If you submit a bid indicating that installation charges may apply without listing those charges, we will consider your bid incomplete and disqualify your bid.

 

Category Two:

VOLUNTARY SITE VISIT – PROJECT A ONLY

Vendors wishing to bid on internal connections can attend a voluntary site visit on December 19th, 2022, at 9am. Vendors will meet at 1200 Carlee Drive, Brenham, TX 77833.   After the Junior High vendors will proceed to the Pride Academy (1301 Market Street, Brenham, TX 77833) campus to view/walk it,  and on to Brenham Early Childhood Learning Center (304 Kerr Street  Brenham,TX 77833) to finish the walkthroughs. Vendors will check in with Rodney Leer.  This will be the districts only site visit. This site visit will be used to show all vendors the existing cabling and cabling closets. The time will be used to escort all attendees around the facilities and critical areas. This will also give vendors time to ask questions about the sites and determine what materials will be required for the project

 

INTERNAL CONNECTIONS

The district is looking to upgrade three school campuses with new multi-gig switches and multi-gig capable wireless access points.

 

New copper cabling will be necessary for all WAPs and current WAPs in school classrooms and hallways. The district will require approximately 173 CAT 6 drops in total. Each drop will have 20’ loop of slack with keystone biscuit termination to allow a patch cable to be connected. Data closet side will need keystone type patch panels installed to accommodate all new runs for termination.

 

Brenham Junior High will need to link MDF and IDF between buildings with about 1,200’ of 6 pair indoor/outdoor rater fiber cabling, installed to five separate buildings on campus.  

 

Project A – Cabling

Installation of 173 drops (runs) of Cat 6 copper cabling in ceiling of school halls and classrooms at three campus locations. Terminate with keystone (biscuit) and roll up 20’ loop in ceilings. Terminate to MDF and IDFs in buildings and mount 24 port keystone patch panels and terminate.

 

Run 1,200’ of 6 pair SM fiber between data closets for five Junior High campus buildings. Cabling will run through building ceilings, existing conduit and lay on building awnings. Terminate all fiber in cassettes and five fiber panels provided by the contractor. Maps and Statement of Work are available for download along with this IFCB.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Antennas, Connectors and Related Components

10

24 Keystone port patch panels

Cabling

173

Copper CAT 6 fiber runs to internal classrooms and hallways at three campus locations. Installation and termination of all cabling.

Cabling

1,200 ft

1,200 ft of 6 pair SM fiber between 5 campus buildings at the Junior High. Five fiber enclosure and cassette terminations. Installation and termination of all cables.

 

 

Project B – Network Equipment

No installation or configuration needed for the switches, WAPs or UPS.  WAPs and switches should include 5 year licensing. A statement of work is available for download along with this IFCB.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Antennas, Connectors and Related Components

10

Cisco network stacking modules. Modules for stacking and interconnecting switches. C9200L-STACK-KIT=

Cabling

23

Stacking cables

Switches

23

Cisco 48 port managed SFP+, PoE+, multi-gig. Cisco Catalyst switch that can be monitored with Cisco Meraki Cloud. C9200L-48PXG4X-EDU. Cisco Digital Network Architecture Essential 5-year term licensing.

UPS/ Battery Backup

12

Tripp Lite 2200 VA with smart AVR WEBCARDLX for central management 2URM – SMART2200RM2UN

Wireless Access Points

90

Cisco Meraki MR46 with 5-year cloud controller license. Medium density WAPs

Wireless Access Points

25

Cisco Meraki MR56 with 5-year cloud controller license. High density WAPs

NOTE: We are requesting WAP or switch licenses on this IFCB, which sometimes may be categorized as BMIC or MIBS by USAC (the BMIC and MIBS boxes on the 470 have been checked to cover this scenario).

 

COMPATIBILITY REQUIREMENT:

WAPs must be compatible with existing Cisco Meraki Cloud console and Cloud controller licensing. Switches must be compatible with existing Cisco Catalyst switches and compatible with Cisco Meraki Cloud controller.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: The applicant will not accept bids from manufacturers of equipment deemed a national security threat by the Federal Communications Commission. The list of prohibited equipment is available here: https://www.fcc.gov/supplychain/coveredlist . Vendors that submit bids that includes these manufacturers will have their bid disqualified.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS – PROJECT B: It will be the bidder’s responsibility to provide documentation about the compatibility requirements listed in this IFCB. Vendors that submit bids without documentation demonstrating the required compatibility listed in this IFCB will have their bids disqualified, unless that vendor has bid the preferred make/model number listed.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components of a single project will be disqualified.

 

Questions Received with Applicant Answers   ( Ask Questions? )




Hi, Secondary Power Supply for all the switches ? MR46 all with internal antennas ? What is the longest/average length of the cable drops ? Additional patch cords ? Cat 6, 6A or 6E ? Is the cabling being replaced or newly installed ? Are there existing fully reusable pathways for the fiber ? Is fiber aerial or buried ? Thank you

Answer:

Question : Secondary Power Supply for all the switches ? No

MR46 all with internal antennas ? YES, only internal.

What is the longest/average length of the cable drops? Ethernet specs limit to 328 ft. Some runs may be close to that length, others shorter. Average will probably be in the 250’ range.

Additional patch cords ? No

Cat 6, 6A or 6E ? Plain Cat 6 Plenum wired TIA 468b

Is the cabling being replaced or newly installed ? Copper newly installed   Good deal of the fiber is replacement

Are there existing fully reusable pathways for the fiber? Some fiber is replacing old fiber and have conduits and existing paths. Other areas it is a new install and will require pulling in ceiling or internal ceiling structures. These are old buildings and it is highly recommended that bidders attend the site survey and walk through on December 19 to put eyes on what is not easily described.

Is fiber aerial or buried? Most of the fiber is in the ceiling, conduit, or laying on an awning roof as shown in the picture submitted.

Do you have conduit available from the right-of-way on South Blue Road onto district property? Does Brenham ISD own conduit between Brenham Middle School and Brenham Junior High? If so, could please provide coordinates and could we pull fiber through the existing conduit in place?

Answer:

Question : Do you have conduit available from the right-of-way on South Blue Road onto district property? No

 

Does Brenham ISD own conduit between Brenham Middle School and Brenham Junior High? No

- Section 3.7 of the “Network Equipment Upgrades” document states “All switches should include SFP+ models see below for quantities”. Can Brenham ISD please clarify if this point is requesting vendors to quote SFP’s? If so, could you please confirm 1) how many? 2) should they be LR (long reach) or SR (short reach)? - In the main IFCB document, the first line of the “Project B – Network Equipment” table shows you’re requesting 10 Stacking Kits. Each stacking kit includes 2 modules and a 50 cm stacking cable. On the second line you’re requesting 23 stacking cables—can you clarify if these are to be tied to the switches in the RFP as well, and what length?

Answer:

Q. Network Equipment Upgrades” document states “All switches should include SFP+ models see below for quantities”. Can Brenham ISD please clarify if this point is requesting vendors to quote SFP’s?           Ans. SFP transceiver modules are not needed. Vendors do not have to quote for SFPs.

 

Q. If so, could you please confirm 1) how many?  N/A. 2) should they be LR (long reach) or SR (short reach)? N/A - In the main IFCB document, the first line of the “Project B – Network Equipment” table shows you’re requesting 10 Stacking Kits. Each stacking kit includes 2 modules and a 50 cm stacking cable. On the second line you’re requesting 23 stacking cables—can you clarify if these are to be tied to the switches in the RFP as well, and what length?  Ans. We are requesting 10 stacking kits  as shown below from Cisco part number (or equivalent) which  include 2 modules and a cable. The SKU for that part shows a 1.6 ft cable as standard.  The 23 refers to the number of switches that we are requesting–C9200L-48PXG4X-EDU (or equivalent) of those some will require stacking and we need the 10 kits that have two modules for each end of the 1.6 ft cable to stack them.

C9200L-STACK-KIT

Stack kit for C9200L SKUs only: Two data stack adapters and one data stack cable

 

1 x stacking cable (external) - 1.6 ft