school Graham ISD
IFCB Posted : Aug 23, 2022
Bid Deadline : Thursday, Sep 29, 2022

Questions Due By : Thursday, Sep 1, 2022
Applicant Address : Graham, TX 76450
IFCB ID : 230000727

IFCB Requirements :

·         All Questions and Bids must be submitted using the on-line IFCB system. If for some reason the system is down before the respective deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission.

 

·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.

 

·         Please include the correct Service Provider Identification Number (SPIN) on your bid.

 

·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.

 

·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See https://www.usac.org/e-rate/service-providers/step-2-responding-to-bids/lowest-corresponding-price/ for details.

 

·         Contracts must not prohibit SPIN changes.

 

·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).

 

·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.

 

·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.

 

·         All contracts awarded under this IFCB bidding process may be voluntarily renewed by the applicant, upon written notice to the provider, for five consecutive one year terms. Please include this language in your final contract.

 

·         All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.

 

·         If the applicant is requesting purchases of new equipment, or maintenance of that new equipment, bids for functionally equivalent equipment will be accepted.

 

·         The winning vendor will be required to complete the USAC approved Item 21 template for the project within 7 working days after notification that the vendor has won the bid.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids from companies that include equipment barred by the Federal Communications Commission due to national security risks (such as ZTE or Huawei) will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids that include equipment that was manufactured for use outside of the United States will be disqualified.

·         DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components of a single project will be disqualified.

 

·         DISQUALIFICATION FACTOR BMIC: Service providers are required to bid the entire maintenance project.  Bids for individual components of the project will be disqualified.

·         DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

·         DISQUALIFICATION FACTOR BMIC: Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.

 


Services and Equipment Requested :

NOTE470/IFCB # 230000725 has been cancelled and replaced with 470/IFCB # 230000727. The original 470/IFCB # 230000725 did not include the Texas purchasing clause on the FCC Form 470.

 

Category Two:

INTERNAL CONNECTIONS

Project A – Firewall

The district currently has an older Sonicwall NSA 6600 and is looking to upgrade and replace this firewall. The district is seeking a Sonicwall or functional equivalent. There are currently 2 x 10 GB SM LC fiber modules in place – one for the uplink to the ISP and one going to the core switch. The firewall is also currently used for routing, point to point VPN, content filtering and other gateway security features. The district would like to retain these features with the new firewall.

 

 All bids must include 3-year warranty and licensing for the firewall. The firewall needs to be installed and configured to work with existing hardware, software, internal and external applications, and communications including but not exclusive to VPN routing, NAT, etc.

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Firewall Service and Components

1

Sonicwall or functional equivalent

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids from companies that include equipment barred by the Federal Communications Commission due to national security risks (such as ZTE or Huawei) will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids that include equipment that was manufactured for use outside of the United States will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components of a single project will be disqualified.

 

 

Project B – UPS

The battery backups will replace older battery backups that have reached end of life. All current switches were replaced, and the new switches require a 20-amp plug. These will need to be a mixture of rack mounted and non-mounted units – 14 x 2 post racks and 10 non rack mounted battery backups. All UPS will need to be installed and connected to existing switches.

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

UPS/Battery Backup

14

APC or functional equivalent – 2 post racks AMP battery backups to connect with existing Aruba 5400 switches with 4 power supplies on most switches.

UPS/Battery Backup

10

APC or functional equivalent – non rack mounted AMP battery backups to connect with existing Aruba 5400 switches with 4 power supplies on most switches.

 

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids from companies that include equipment barred by the Federal Communications Commission due to national security risks (such as ZTE or Huawei) will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids that include equipment that was manufactured for use outside of the United States will be disqualified.

DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid an entire Project A or Project B.  Bids for individual components of a single project will be disqualified.

 

BASIC MAINTENANCE OF INTERNAL CONNECTIONS:

The district would like a 3-year manufacturer’s support contract for these items:

 

Type of Equipment

Quantity Vendor Should Bid

 

Preferred Make/Manufacturer

Firewall Service and Components

1

Sonicwall or functional equivalent

DISQUALIFICATION FACTOR BMIC: Service providers are required to bid the entire maintenance project.  Bids for individual components of the project will be disqualified.

DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

DISQUALIFICATION FACTOR BMIC: Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.

 


There is an additional document associated with this IFCB. Please click the buttons to download the document.

Graham_C2_COVER_PAGE1.pdf
2023_C2_Bidding_Instructions5.docx

Questions Received with Applicant Answers   ( Ask Questions? )




1. For the firewall project the RFP states "content filtering and other gateway security features". Can you please elaborate on what specific security features the district needs, some services may require an additional license to be quoted. 2. For the "non rack mounted" UPS's does the district want a tower form factor, or a rack mount UPS on vertical stands?

Answer:

1: Gateway antivirus, intrusion prevention, Geo-IP filtering, and botnet filtering. 

 

2: Either will work, just wanted to ensure vendors know that there is not a rack to mount the UPS in. 

1) Is it a requirement to quote both projects? 2) What is the runtime required for the battery backups, 30 minutes, 1 hour, more?

Answer:

1:Each project can be bid independently. 

 

2: 30 minutes would be the minimum, but 1 hour would be preferable. 

Hi, regarding the Project B. Do you need twenty four UPS units ? Can you please share the part numbers of the old items that you are looking to replace ? Do you have the preferred UPS part numbers for the new items ? Thank you

Answer:
Yes, 24 different UPS's as they will each be at a different location. The part numbers are irrelevant since the existing UPS's  will be removed and replaced. Most are 10+ year old APC 2000+ units, but do not support 20amps. I do not have preferred UPS numbers.

Could you please provide me which power supply wattage you have? 700W, 1100W, or 2750W

Answer:
2750W is what we are requesting

Could you please let me know which Sonic Wall device do you need?

Answer:
NSa 6700

I need to apply for a SPIN number but do not have your 499 Filer ID. How do I get this information?

Answer:

You do not need any information from an applicant to obtain a SPIN number. We suggest you call the Customer Service Bureau at 888.203.8100 for help obtaining a SPIN number.

Could you please provide me that Do you need a licence and a 3 year warranty just for the Firewall or APC UPS.

Answer:

Just the firewall. 

Per APC What is the total load for each UPS and what is the plug type for the switches?

Answer:
Minimum 1500V. NEMA 5-20

Are you currently using 120V or 240 single phase for the supply voltage? What type of outlet is currently supplying the switches?

Answer:
120v. NEMA 5-20