All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.
· All Questions and Bids must be submitted using the on-line IFCB system. If the IFCB system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission.
· Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.
· Please include the correct Service Provider Identification Number (SPIN) on your bid.
· By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.
· Bidder is expected to provide the lowest corresponding price per E-rate rules. See http://www.usac.org/sl/service-providers/step02/lowest-corresponding-price.aspx for details.
· Contracts must not prohibit SPIN changes.
· Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).
· Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12-month period. This does not apply to the recent FCC exemptions of the Gift Rule for the COVID pandemic.
· All contracts awarded will be contingent upon E-rate funding and final board approval. The applicant may choose to do all or part of the project upon funding notification.
· All contracts awarded under this IFCB bidding process may be voluntarily renewed by the applicant, upon written notice to the provider, for five consecutive one-year terms. Please include this language in your final contract.
· All applicable fees, surcharges, and taxes must be identified on the bid or your bid will be disqualified. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. If the applicant discovers that fees, taxes or surcharges apply but are not listed on the bid (after the time of bid awards) those charges will be the responsibility of the bidding company.
· The winning vendor will be required to complete the USAC approved Item 21 template for the project within 7 working days after notification that the vendor has won the bid.
· DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B & C: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
· DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Bids from companies that include equipment barred by the Federal Communications Commission due to national security risks (such as ZTE or Huawei) will be disqualified.
· DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A & B ONLY : Vendors who wish to bid on Project A and/or Project B must attend one of two mandatory site visits. Vendors who submit a bid but have not attended a meeting will be disqualified.
· DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Service providers are required to bid an entire project/upgrade. Bids for individual components of a project/upgrade will be disqualified.
· DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.
· DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Bids that include equipment that was manufactured for use outside of the United States will be disqualified.
· DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
· DISQUALIFICATION FACTOR BMIC: Service providers are required to bid the entire hardware project/upgrade. Bids for individual components of the project/upgrade will be disqualified.
· DISQUALIFICATION BMIC - Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified. Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment. Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.
UPDATE 11/18/20: A network map has been added
CATEGORY TWO
MANDATORY SITE VISIT – INTERNAL CONNECTIONS PROJECT A & B ONLY
Vendors wishing to bid on Category Two must attend one of two mandatory site visits on either November 9th or November 16th. Vendors should RSVP to Dusty Malena at dusty.malena@boonevilleschools.com to set up a time for a site visit on November 9th or November 16th. Vendors will need to report to the front office of the Junior High School at 835 East 8th Street, Booneville AR 72927, and ask for Dusty Malena. Vendors are required to wear masks while inside the buildings. THIS EMAIL IS TO RSVP ONLY. ALL QUESTIONS AND BIDS MUST STILL BE SUBMITTED VIA THE IFCB. BIDS NOT SUBMITTED VIA THE IFCB WILL BE DISQUALIFIED.
INTERNAL CONNECTIONS
PROJECT A – SWITCHES (Equipment only)
This project is for equipment only. Do not include any installation or provisioning costs.
Type of Equipment |
Quantity Vendor Should Bid
|
Preferred Make/Manufacturer |
Switches |
1 |
Juniper EX4600-40F-AFO or functional equivalent |
Switches |
2 |
Juniper EX2300-24T or functional equivalent |
Switches |
2 |
Juniper EX-4PST-RMK or functional equivalent |
Switches |
12 |
Juniper EX-SFP-10GE-SR or functional equivalent |
Switches |
10 |
Juniper EX-SFP-10GE-LR or functional equivalent |
Switches |
38 |
Ubiquiti USW-PRO-48 or functional equivalent |
Switches |
21 |
Ubiquiti US-PRO-48-POE or functional equivalent |
Switches |
8 |
Ubiquiti UF-SM-10G or functional equivalent |
Switches |
92 |
Ubiquiti UF-MM-10G or functional equivalent |
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A & B ONLY : Vendors who wish to bid on Project A and/or Project B must attend one of two mandatory site visits. Vendors who submit a bid but have not attended a meeting will be disqualified.
PROJECT B – SWITCHES (Installation & provisioning only)
This project is for installation and provisioning of the switches for VLANS only. Do not include any equipment costs.
Type of Equipment |
Quantity Vendor Should Bid
|
Preferred Make/Manufacturer |
Switches |
1 |
Juniper EX4600-40F-AFO or functional equivalent |
Switches |
2 |
Juniper EX2300-24T or functional equivalent |
Switches |
2 |
Juniper EX-4PST-RMK or functional equivalent |
Switches |
12 |
Juniper EX-SFP-10GE-SR or functional equivalent |
Switches |
10 |
Juniper EX-SFP-10GE-LR or functional equivalent |
Switches |
38 |
Ubiquiti USW-PRO-48 or functional equivalent |
Switches |
21 |
Ubiquiti US-PRO-48-POE or functional equivalent |
Switches |
8 |
Ubiquiti UF-SM-10G or functional equivalent |
Switches |
92 |
Ubiquiti UF-MM-10G or functional equivalent |
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A & B ONLY : Vendors who wish to bid on Project A and/or Project B must attend one of two mandatory site visits. Vendors who submit a bid but have not attended a meeting will be disqualified.
PROJECT C – UPS DEVICES
Type of Equipment |
Quantity Vendor Should Bid
|
Preferred Make/Manufacturer |
UPS/Battery Backup |
8 |
APC 1500VA or functional equivalent |
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B & C: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Bids from companies that include equipment barred by the Federal Communications Commission due to national security risks (such as ZTE or Huawei) will be disqualified.
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Service providers are required to bid an entire project/upgrade. Bids for individual components of a project/upgrade will be disqualified.
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS PROJECTS A, B AND C: Bids that include equipment that was manufactured for use outside of the United States will be disqualified.
BASIC MAINTENACE OF INTERNAL CONNECTIONS
The district is requesting a 16 hour block of time per month to maintain all the switches requested under Internal Connections Project A, including on-site maintenance if needed.
DISQUALIFICATION FACTOR BMIC: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
DISQUALIFICATION FACTOR BMIC: Service providers are required to bid the entire hardware project/upgrade. Bids for individual components of the project/upgrade will be disqualified.
DISQUALIFICATION BMIC - Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified. Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment. Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.
Booneville_C2_COVER_PAGE.pdf |
2021_C2_Bidding_Instructions78.pdf |
Booneville_School_District_Network.pdf |
Answer:
No, installation is not required for project C.
Answer:
Project A is just equipment and can be bid separately.
The BMIC should be bid along with the provisioning and installation of the switches (Project B), so that the company doing the maintenance will be familiar with the equipment we are having installed, as well as the physical layout of the district.
Answer:
Mandatory site visits are required for Projects A and B. Vendors that bid Projects A and B but don't attend a site visit will have their bid disqualifed.
Answer:
We are not going to waive the mandatory site visit for project A&B; there will be no virtual site visits.
Answer:
I don't have a map of the district network as it is laid out topographically. I've attached a map of the network to the IFCB as it pertains to individual buildings. Then a person could look at Google maps to get an idea of the location of the buildings themselves.