All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school Monticello School District
IFCB Posted : Nov 18, 2016
Bid Deadline : Monday, Dec 19, 2016

Questions Due By : Monday, Dec 12, 2016
Applicant Address : Monticello, AR 71655
IFCB ID : 170050794

IFCB Requirements :
 ·         All Questions and Bids must be submitted using the on-line IFCB system. If for some reason the system is down before the respective deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission.
 
·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.
 
·         Bids must identify all fees and charges (including installation charges, if applicable) that will be assessed to the Applicant to procure the services or equipment included in your bid.
 
·         Please include the correct Service Provider Identification Number (SPIN) on your bid.
 
·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.
 
·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See http://www.usac.org/sl/service-providers/step02/lowest-corresponding-price.aspx for details.
 
·         Contracts must not prohibit SPIN changes.
 
·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).
 
·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period.
 
·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.
 
·         All contracts awarded under this IFCB bidding process may be voluntarily renewed by the applicant, upon written notice to the provider, for five consecutive one year terms. Please include this language in your final contract.
 
·         All applicable fees, surcharges, and taxes must be identified on the bid. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. Fees and surcharges that apply but are not listed on the bid will be the responsibility of the bidding company, should their bid be awarded.
 
·         If the Applicant is requesting bids for equipment with specific make and model numbers listed, the Applicant will also accept bids for functionally equivalent equipment.
 
·         The winning vendor will be required to complete the USAC approved Item 21 template for the project within 7 working days after notification that the vendor has won the bid.
 
·         DISQUALIFICATION BMIC - Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.
 
·         DISQUALIFICATION FACTOR C2: Service providers are required to bid the entire hardware project/upgrade.  Bids for individual components of the project/upgrade will be disqualified.
 
·         DISQUALIFICATION FACTOR C2: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.

Services and Equipment Requested :
UPDATE 12/13/16: FLOOR PLANS HAVE BEEN ADDED

CATEGORY TWO DISQUALIFICATION FACTORS:
 
·         Service providers are required to bid the entire hardware project/upgrade.  Bids for individual components of the project/upgrade will be disqualified.
·         Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
·         DISQUALIFICATION BMIC - Maintenance bids listing only an hourly rate and not a monthly or annual total will be disqualified.  Vendors quoting an hourly rate are required to also a) confirm that you have the ability/expertise to maintain all of the equipment listed and b) propose a number of hours at a particular rate monthly to properly maintain the entire list of equipment.  Bids that contain only hourly rates, without confirmation that the company can service the list of equipment, or without a monthly total will be disqualified.
 

CATEGORY TWO PROJECT DETAILS
:
 
Applicant has two separate Category Two Projects:  Project A for Internal Connections and Project B for Basic Maintenance.  Project A includes:  installation of Cat6 cabling, patch cables and cable ends from switch closets to client devices.
 
The winning vendor will be required to complete the USAC approved Item 21 template for the project within 7 working days after notification that the vendor has won the bid.
 
 
CATEGORY TWO VOLUNTARY WALK THROUGHS:
 
Voluntary walk throughs will be from December 1st through December 9th, excluding the weekend.  Applicant will accept emails from vendors from 8AM – 4PM for setting up scheduled walk throughs.  Interested vendors should email michael.reed@billies.org.  This email address is to schedule a walk through only, all questions and bids must be submitted via the Submit a Question/Upload a Bid buttons.  Vendors will need to meet at the Technology Building (located behind the Central Office) at 935 Scogin Drive, Monticello, AR 71655.
    

There is an additional document associated with this IFCB. Please click the buttons to download the document.

2017C2BiddingInstructions43.pdf
MonticelloC2COVERPAGE.pdf
MonticelloC2EquipmentList.xlsx
MontFloorPlansUploaded.pdf

Questions Received with Applicant Answers   ( Ask Questions? )




1. Are the requested wireless APs needing to be controller based or cloud based? 2. Can you provide a basis for type of access point? Usually we provide options for "ac" wave 1 or wave 2 access points as 2x2, 3x3, or 4x4 Mimo units. Thank you.

Answer:
 The AP controller will be cloud-based.

Do you have a map of where cabling needs to be installed

Answer:
 Floor plans have been posted as an attachment to the IFCB. They do not include the drop locations…the cabling is a total rewire to all computers, printers and all other networked devices.

Should cabling for Project A be plenum rated cable?

Answer:
 No

Should removal of existing cabling in Project A be included in bids?

Answer:
 removal of existing wire is included

Does the scope of work include relocating any existing AP's?

Answer:
 No on relocation APs...the new project will replace all APs in the High School.