All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.
UPDATE 2/15: A SPREADSHEET HAS BEEN ADDED FOR LIT FIBER PRICING.
UPDATE 2/12: FOR THE LIT FIBER REQUESTS, WE WOULD LIKE TO SEE BIDS AT A 3 OR 5 YEAR TERM, PLUS A FULL 10 YEAR TERM.
UPDATE 2/3: the requirement for vendors to obtain SPIN before bid submission has been removed (we encourage bidders to obtain one ASAP, but it is no longer a disqualification factor).
Self-Provisioned Fiber – For 2 schools plus equipment. Applicant will accept bids for functional equivalents when a preferred make/manufacturer is listed. There is an additional zip file with information to download for this project. Applicant is requesting a payment plan of 4 years for construction costs of circuit.
DISQUALIFICATION FACTOR: There is a mandatory pre-bid conference Friday, January 29, 2016 at 2:00 pm. Bidder should meet at Gretna Public Schools Administration Building located at 11717 South 216th Street, Gretna, NE 68028. Bids received from vendors who did not attend the pre-bid conference will be disqualified.
GretnaSelfProvisionedFiberDocs.zip |
LitLeasedPricingSheet.xlsx |
Answer:
The lit fiber should be terminated into a SC type fiber panel. We will then use SC-LC fiber patch cables (single-mode) to connect to a 10gig port on our switch. We do not currently have switches purchased yet but have DLink DGS-3620 listed as our preferred equipment on the 470. The DGS-3620 is a layer 2-3 switch that is already the currently connectivity switch at our other buildings.
Answer:
Per Section 017300.3.3.B, the surveying is the responsibility of the contractor.
Answer:
A no crop area will be established providing a 25 ft buffer from the fiber optic line. This area will be from the south property line to thirty (30) feet to the north, from 180th Street to west to 183rd Street. A no crop area will be established from the north property line ninety (90) feet to the south, from 180th Street 475 feet west, then from the north property line 55 feet south extending west to the Waters of the U.S. Any crop damage incurred outside of these limits will be the contractors responsibility.
Answer:
No As-Built drawings available, general boring depth was 15ft except at Handholes which are approximately 4-5ft deep.
Answer:
No the slack loop at Cornhusker Rd is to remain. The fiber optic cable will be cut at both locations noted by Keyed Note No. 10 and No. 2 and all 24 strands spliced to the new fiber optic cable. The existing fiber optic cable between the these locations will be abandoned.
Answer:
Keyed Note No. 3 should be moved to marker post by handhole HH-1 shown approximately 500ft West.
Answer:
For each duct installed under separate contract, a nylon pull cord is specified to be installed in each duct by that separate contractor.