school Caney Valley USD 436
IFCB Posted : Feb 6, 2015
Bid Deadline : Friday, Mar 6, 2015

Questions Due By : Friday, Feb 27, 2015
Applicant Address : Caney, KS 67333
IFCB ID : 135310001320653

IFCB Requirements :
·         All Questions and Bids must be submitted using the on-line IFCB system. If for some reason the system is down before the respective deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission.
 
·         Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.
 
·         Please include the correct Service Provider Identification Number (SPIN) on your bid.
 
·         By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.
 
·         Bidder is expected to provide the lowest corresponding price per E-rate rules.  See http://www.usac.org/sl/service-providers/step02/lowest-corresponding-price.aspx for details.
 
·         Contracts must not prohibit SPIN changes.
 
·         Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).
 
·         Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period.
 
·         All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.
 
·         All contracts awarded under this IFCB bidding process may be voluntarily renewed by the applicant, upon written notice to the provider, for five consecutive one year terms.
 
·         DISQUALIFICATION FACTOR project 1: Vendors must use the Year 18 Required IC Template when submitting a bid. Vendors that submit bids that do not use this template will have their bids disqualified. See IFCB for details.
 
·         DISQUALIFICATION FACTOR PROJECT 1: VENDORS WISHING TO SUBMIT BIDS FOR PROJECT 1 MUST ATTEND A MANDATORY SITE VISIT DURING THE DATES LISTED BELOW. BIDS RECEIVED FROM VENDORS WHO DID NOT ATTEND A MEETING WILL BE DISQUALIFIED.
·       
 
DISQUALIFICATION FACTOR project 2: Vendors must use the Year 18 Required IC Template when submitting a bid. Vendors that submit bids that do not use this template will have their bids disqualified. See IFCB for details.
 
·         DISQUALIFICATION FACTOR PROJECT 2: VENDORS WISHING TO SUBMIT BIDS FOR PROJECT 2 MUST ATTEND A MANDATORY SITE VISIT DURING THE DATES LISTED BELOW. BIDS RECEIVED FROM VENDORS WHO DID NOT ATTEND A MEETING WILL BE DISQUALIFIED.
 
·         DISQUALIFICATION FACTOR BMIC: MAINTENANCE BIDS LISTING ONLY AN HOURLY RATE AND NOT A MONTHLY OR ANNUAL TOTAL WILL BE DISQUALIFIED.  VENDORS QUOTING AN HOURLY RATE ARE REQUIRED TO ALSO A) CONFIRM THAT YOU HAVE THE ABILITY/EXPERTISE TO MAINTAIN ALL OF THE EQUIPMENT LISTED AND B) PROPOSE A NUMBER OF HOURS AT A PARTICULAR RATE MONTHLY TO PROPERLY MAINTAIN THE ENTIRE LIST OF EQUIPMENT.  BIDS THAT CONTAIN ONLY HOURLY RATES, WITHOUT CONFIRMATION THAT THE COMPANY CAN SERVICE THE LIST OF EQUIPMENT, OR WITHOUT A MONTHLY TOTAL, WILL BE DISQUALIFIED.
 
·         DISQUALIFICATION FACTOR BMIC: Vendors must use the Year 18 Required BMIC Template when submitting a bid. Vendors that submit bids that do not use this template will have their bids disqualified. See IFCB for details.
 
·         If bidding Category 2: E-rate rules require Category Two budgets to be calculated by each individual school. In order to accurately track those budgets, please break up your bid by each school.
 
 

Services and Equipment Requested :
 category two:

The Caney Valley School District will need a network infrastructure upgrade project which will include wireless access points, wireless controllers, switches, cabling, racks, router, caching servers, firewall and UPS devices as needed.

PROJECT 1 – nETWORK UPGRADE:

DISQUALIFICATION FACTOR PROJECT 1:
Because USAC now requires data-entry of every line item on a contract, vendors bidding on the Category Two Internal Connections request are REQUIRED to submit bids using the “Year 18 Required IC Template.” Vendors that submit bids that do not use this template will have their bids disqualified. Please be aware that this a new requirement of CRW Consulting. Please see the ATTACHED instructions document for more detail.

DISQUALIFICATION FACTOR PROJECT 1:
Vendors wishing to SUBMIT BIDS FOR CATEGORY TWO project must attend a mandatory SITE ON EITHER fEBRUARY 17, 2015 AT 9:00 AM OR FEBRUARY 24, 2015 AT 9:00 AM at the high school 601 e. bullpup blvd. PLEASE RSVP TO dcarey@caney.com IF ATTENDING. This email is to RSVP only. All questions and bids must still be submitted via the IFCB.
 
If bidding Category 2: E-rate rules require Category Two budgets to be calculated by each individual school. In order to accurately track those budgets, please break up your bid by each school.

There is an additional document available for download which provides details for the Applicant’s Category 2 project.

PROJECT 2 - CABLING:

DISQUALIFICATION FACTOR PROJECT 2:
Because USAC now requires data-entry of every line item on a contract, vendors bidding on the Category Two Internal Connections request are REQUIRED to submit bids using the “Year 18 Required IC Template.” Vendors that submit bids that do not use this template will have their bids disqualified. Please be aware that this a new requirement of CRW Consulting. Please see the ATTACHED instructions document for more detail.

DISQUALIFICATION FACTOR PROJECT 2:
Vendors wishing to SUBMIT BIDS FOR CATEGORY TWO project must attend a mandatory SITE ON EITHER fEBRUARY 17, 2015 AT 9:00 AM OR FEBRUARY 24, 2015 AT 9:00 AM at the high school 601 e. bullpup blvd. PLEASE RSVP TO dcarey@caney.com IF ATTENDING. This email is to RSVP only. All questions and bids must still be submitted via the IFCB.
 
If bidding Category 2: E-rate rules require Category Two budgets to be calculated by each individual school. In order to accurately track those budgets, please break up your bid by each school.

There is an additional document available for download which provides details for the Applicant’s Category 2 project.

Basic Maintenance of Internal Connections:

DISQUALIFICATION FACTOR BMIC
: MAINTENANCE BIDS LISTING ONLY AN HOURLY RATE AND NOT A MONTHLY OR ANNUAL TOTAL WILL BE DISQUALIFIED.  VENDORS QUOTING AN HOURLY RATE ARE REQUIRED TO ALSO A) CONFIRM THAT YOU HAVE THE ABILITY/EXPERTISE TO MAINTAIN ALL OF THE EQUIPMENT LISTED AND B) PROPOSE A NUMBER OF HOURS AT A PARTICULAR RATE MONTHLY TO PROPERLY MAINTAIN THE ENTIRE LIST OF EQUIPMENT.  BIDS THAT CONTAIN ONLY HOURLY RATES, WITHOUT CONFIRMATION THAT THE COMPANY CAN SERVICE THE LIST OF EQUIPMENT, OR WITHOUT A MONTHLY TOTAL, WILL BE DISQUALIFIED.

DISQUALIFICATION FACTOR BMIC:
Because USAC now requires data-entry of every line item on a contract, vendors bidding on the Category Two Basic Maintenance of Internal Connections request are REQUIRED to submit bids using the “Year 18 Required BMIC Template.” Vendors that submit bids that do not use this template will have their bids  disqualified. Please be aware that this a new requirement of CRW Consulting. PLEASE SEE THE ATTACHED INSTRUCTIONS DOCUMENT FOR MORE DETAIL.
 
If bidding Category 2: E-rate rules require Category Two budgets to be calculated by each individual school. In order to accurately track those budgets, please break up Your bid by each school.

There is an additional document associated with this IFCB. Please click the buttons to download the document.

Year18RequiredICTemplate46.xlsm
Year18RequiredBMICTemplate100.xlsm
Year18RequiredTemplateInstructions32.pdf
CaneyValleyC2Project.pdf

Questions Received with Applicant Answers   ( Ask Questions? )




It is noted on the Project notes that HP switches and Array WiFi products are requested. Will any other brands be accepted for the bid or must the bid items be HP and Array?

Answer:
 E-rate rules require applicants to accept bids for “functionally equivalent equipment.” The district may choose to award more points to those vendors that bid the preferred solution.

My questions is would the use of a flexible fabric innerduct, MaxCell, be considered for use in this project. We have a new Self-supporting Plenum product which contains a galvanized steel cable in the top which allows it to be hung on or off almost anything; beams, cable tray, j-hooks. Fully loaded it can contain 72 Cat 6 cables and is supported every 10 feet. The standard outside plant MaxCell can be used in OSP applications. You can go to our web site to view much more information covering MaxCell; www.maxcell.us.

Answer:
 Yes, we will consider it.

During the walk through it was stated not to include patch panels or patch cables. These are required to meet BICSI Installation Standard and Manufacturers Warranty if needed. Do these need to be added?

Answer:
 Please do bid patch panels and patch cables. We apologize for the misunderstanding.