Answer:
Those documents are attached to this IFCB, see the links right above the "services and equipment requested" section of this IFCB.
Answer:
1. Does the district have a cabling manufacturer preference? No
2. Is a warranty required for the cabling and if so how long? No, but a full quality and line check will be done prior to payment
3. Does the new school have any data closets? If so, how many? The attached drawing does not indicate. Yes. The floor plan has areas marked for building facilities (labeled “STOR.”, “MECH.”, or “CUST” on the pdf version of the plan, non-restroom grey areas on the .jpg plan). These will be possible areas for cabling closets to be determined further along. My estimate is that 2 data closets will be needed.
4. What equipment is required in the data closet - 7\' racks, cabinets etc? A 7’ rack in each closet (2 total estimated)
5. If there are data closets, does the district want them connected with fiber? If so, how many strands and what would be the type of fiber desired? (.5 micron or .625 micron) Yes. 4 strand .625 micron cables between closets will suffice.
6. Is the district desiring a complete \'turn-key\' cabling solution or should a bid response price only the items listed in the RFP? (Complete cable management, grounding bounding, closet construction with appropriate rack/cabinets, pathway etc.) Yes, ‘turn-key’ is a good description of what we’re looking for. I really don’t want to have to terminate the lines, fasten them above drop ceilings, or so on.
7. Does the district require any deliverables for the cabling plant? (Drawings, test results for copper and fiber, warranty) Both ends of all cabling will need to be labeled. Drawings would be nice, but any easily read documentation that shows where each line is going to, and coming from, will suffice. Copper and fiber test results would be a plus, but not required. Local testing will be done to ensure completion regardless, but if you have reports as a result of your own testing they would be much appreciated.
Answer:
I'm not sure what we would walk you through, the hardware requested on this IFCB is for new a building, construction has not started yet. The best documentation we have are the floor plans attached to this IFCB.
Answer:
1. Regarding Hosted VoIP system, is the current count of 55 for all existing phones in the district, and then we assume an increase to bring the total to 75 after the completion of the new Middle School, or are all 75 for the Middle School? 55 is the count of phones needed to support the building based on floor plans. This count includes offices and classrooms. 75 is the number for growth purposes. We do not want a system that can only handle 55 lines, only to have to completely replace it should we need a handful more at some point.
Answer:
E-rate rules require us to be specific about the equipment we are requesting. Please bid the equipment requested on the 470 and on this IFCB.
Answer:
We run N-standard access points with Gigabit Ethernet over Cat5e cabling in district now, so I do not see the need for the added expense of the Cat6 cabling.
Answer:
Yes, you may submit bids for individual components of this IFCB. Vendors are not required to bid all services. If we required bids for all components/services listed we would make sure we have that clearly stated as a disqualification factor on this IFCB.
Answer:
Yes, you may submit bids for individual components of this IFCB. Vendors are not required to bid all services. If we required bids for all components/services listed we would make sure we have that clearly stated as a disqualification factor on this IFCB.