All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.

school White Hall School District
IFCB Posted : Feb 14, 2020
Bid Deadline : Friday, Mar 13, 2020

Questions Due By : Wednesday, Feb 19, 2020
Applicant Address : White Hall, AR 71602
IFCB ID : 200024086

IFCB Requirements :
 • All Questions and Bids must be submitted using the on-line IFCB system. If the IFCB  system is down before the deadline, please email your bid to info@crwconsulting.com or fax it to 918.445.0049. Bids or questions submitted in this fashion will be disqualified if the on-line system is active at the time of submission.
 
Bidder must agree to participate in USF Program (AKA “E-rate”) for the corresponding funding year.
 
Please include the correct Service Provider Identification Number (SPIN) on your bid.
 
By submitting a bid, bidder certifies that the bidder does have a valid (non-red light status) SPIN for the E-rate program at the time of submission. Should the Applicant discover that the bidder is on red light status, or if the FCC classifies the bidder as on red-light status before work is performed and invoices are paid, the contract will be null and void and the applicant will have no payment obligations to the bidder.
 
Bidder is expected to provide the lowest corresponding price per E-rate rules.  See http://www.usac.org/sl/service-providers/step02/lowest-corresponding-price.aspx for details.
 
Contracts must not prohibit SPIN changes.
 
Bidder must agree to provide the Applicant the choice of discount methods (SPI or BEAR).
 
Bidder will be automatically disqualified if the District determines that the bidding company has offered any employee of the District any individual gift of more than $20 or gifts totaling more than $50 within a 12 month period.
 
All contracts awarded will be contingent upon E-rate funding and final board approval.  The applicant may choose to do all or part of the project upon funding notification.
 
All contracts awarded under this IFCB bidding process may be voluntarily renewed by the applicant, upon written notice to the provider, for five consecutive one year terms. Please include this language in your final contract. 
 
All applicable fees, surcharges, and taxes must be identified on the bid or your bid will be disqualified. E-rate rules require the applicants to evaluate the price of eligible goods and services that will be listed on the 471 application during the competitive bidding process. If the applicant discovers that fees, taxes or  surcharges apply but are not listed on the bid (after the time of bid awards) those charges will be the responsibility of the bidding company.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire hardware project/upgrade.  Bids for individual components of the project/upgrade will be disqualified.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids that include equipment that were manufactured for use outside of the United States will be disqualified.

Services and Equipment Requested :
Internal Connections – There is an additional attachment for download that lists equipment being requested. Applicant will accept functional equivalent of all items. No installation is needed for any equipment.
 
NOTE:  The BMIC box has been checked on the 470 in the event that your licenses are considered BMIC (not IC) by USAC.  Bid those costs, if any, under Internal Connections on the cover page.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Vendors must complete and include the C2 Cover Page with their bid. Bids received without the cover page will be disqualified.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Service providers are required to bid the entire hardware project/upgrade.  Bids for individual components of the project/upgrade will be disqualified.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.
 
DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Bids that include equipment that were manufactured for use outside of the United States will be disqualified.
 

There is an additional document associated with this IFCB. Please click the buttons to download the document.

WhiteHallEquipmentList.xlsx
WhiteHallC2CoverPage.docx
2020C2BiddingInstructions2056.pdf

Questions Received with Applicant Answers   ( Ask Questions? )




What specific equipment is being connected to each UPS in each closet for each school?

Answer:
 

The primary equipment that will be installed and monitored via UPS Chute controllers will be the following: Aruba Mobility Masters and controllers, Cisco Switches and routers, Servers (Domain controllers, etc.), At&t Fiber Handoffs, POE Switches, Layer 2/Layer 3 failover infrastructure.