All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.
Type of Equipment
|
School Name
|
Number of Devices Vendor Should Bid
|
Preferred Make/Manufacturer
|
Racks
|
Nichols Elementary
|
1
|
No Preference
|
Type of Equipment
|
School Name
|
Number of Devices Vendor Should Bid
|
Preferred Make/Manufacturer
|
Switches
|
Nichols Elementary
|
1
|
Juniper EX3200 or functional equivalent
|
Switches
|
Roosevelt Elementary
|
1
|
Juniper EX3200 or functional equivalent
|
Switches
|
Wilson Elementary
|
1
|
Juniper EX3200 or functional equivalent
|
Switches
|
Washington Elementary
|
1
|
Juniper EX3200 or functional equivalent
|
Switches
|
Rockdale Elementary
|
1
|
Juniper EX3200 or functional equivalent
|
Switches
|
Miami High School
|
2
|
Juniper EX3200 or functional equivalent
|
Switches
|
Will Rogers Middle School
|
2
|
Juniper EX3200 or functional equivalent
|
Type of Equipment
|
School Name
|
Number of Devices Vendor Should Bid
|
Preferred Make/Manufacturer
|
UPS/Battery Backup
|
Nichols Elementary
|
2
|
APC or functional equivalent
|
UPS/Battery Backup
|
Roosevelt Elementary
|
2
|
APC or functional equivalent
|
UPS/Battery Backup
|
Wilson Elementary
|
1
|
APC or functional equivalent
|
UPS/Battery Backup
|
Washington Elementary
|
1
|
APC or functional equivalent
|
UPS/Battery Backup
|
Rockdale Elementary
|
1
|
APC or functional equivalent
|
UPS/Battery Backup
|
Miami High School
|
3
|
APC or functional equivalent
|
UPS/Battery Backup
|
Will Rogers Middle School
|
2
|
APC or functional equivalent
|
Type of Equipment
|
School Name
|
Number of Devices Vendor Should Bid
|
Preferred Make/Manufacturer
|
Wireless Controller
|
Roosevelt Elementary
|
1
|
Aruba 7210 or functional equivalent
|
2019C2BiddingInstructions20.docx |
C2COVERPAGE8758.pdf |
Answer:
I would like a 3300 - 48 port POE Juniper Switch (or functional equivalent). Please make sure you read all of the requirements in the IFCB: DISQUALIFICATION FACTOR INTERNAL CONNECTIONS: Applicant will not accept bids for refurbished equipment. Any bids containing refurbished equipment will be disqualified.
Answer:
Rack Mounted, No Onsite installation is needed, 1500VA to 2200 VA is size at each site.
Answer:
Switches is what are going to be on the Battery backup. There will probably be 3 - 5 switches per battery backup. Rackmount. E-rate will only pay for short term UPS devices, approx. 20-40 minutes.
Answer:
No bids will be accepted via mail, all bids must be submitted through the website. Each school’s address is at the top of the IFCB.
Answer:
Licensing for just the controller box
Answer:
Locking frame rock