Type of Equipment
|
School Name
|
Specific Quantity
|
Preferred Make/Manufacturer
|
Cabling
|
Olive High School
|
425Ft
|
No Preference
|
Wireless Access Points
|
Olive High
|
25
|
No Preference
|
Type of Equipment
|
School Name
|
Specific Quantity
|
Preferred Make/Manufacturer
|
Wireless Access Points
|
Olive Elementary
|
12
|
No Preference
|
Type of Equipment
|
School Name
|
Specific Quantity
|
Preferred Make/Manufacturer
|
Switches
|
District Shared
|
3
|
Extreme 48 Port or functional equivalent
|
UPS/Battery Backup
|
District Shared
|
2
|
No Preference
|
Wireless Controller
|
District Shared
|
2
|
No Preference
|
2018C2BiddingInstructions3.docx |
OliveC2COVERPAGE.pdf |
Answer:
we need cat 6 all overhead.
Answer:
Yes
Answer:
10-15 minute uptime is fine. We will be connecting two servers and multiple 48 port POE switches to any UPS solution provided
Answer:
This is addition to what is already being used. We will have 29 users per AP
Answer:
1. Is PoE desired, if so how many ports per switch? POE is desired, perferred that all switch ports use it
2. How many ports are desired on each switch? 48
3. Is there fiber uplinks needed? Fiber uplinks will be needed to link existing switches into network.
4. Is stacking required on the switches? No but preferred
5. What switches are currently in use? Extreme switches
6. Is there a specific model number that you preferred No specific model preferred, but compatibility with existing
Answer:
10-15 minute uptime is fine. We will be connecting two servers and multiple 48 port POE switches to any UPS solution provided
Answer:
We would be happy to provide that form to the winning bidder after the bid evaluations have taken place.
Answer:
10 gig or higher not sure of the kind of fiber
Answer:
I’m not so sure on densities, though I want the highest for the high school, given the number of chromebooks we have and with more on the way.
Answer:
More than 24. I want to have a controller that in theory could support as many WAPs
Answer:
We have one drop that is 425 ft then we will need what it takes to get our AP operational.
Answer:
Yes, Wednesday November 1st at 9 am. Go to 9352 South 436th West Avenue, Drumright, OK 74030 and ask for Jimmy Reynolds.