All bid deadlines are 11:59pm Pacific Time the date of the bid deadline listed unless otherwise noted.
1.) Is this a wage prevailing state? Yes
2.) Is this job taxable? Don't Know
3.) What color wire do we want telephones to be? Blue
4.) Do we use Wire trays or J Hooks in the 500 building at Washington Middle School? WMS Wire Trays 500 Building5. How to get the connections to the portables? Different ways at different locations.
6. How to handle 134 and 135 at Barton? Run to the MDF.
7. We do want Rm 509 and Room 607 rewired after all? Yes
8. Since CAT6A bend radiuses will not work on flat panels in smaller cabinets how to handle that? With proper raceway.
9. How to allow for cable management pieces in the racks? Put in cable management that fits.
10. Whether or not to use metal or plastic surface mount conduit in rooms without hollow walls and no drop ceilings? Plastic raceway.
11. How often to anchor surface mount conduit? Follow industry standard.
12. How many cables allowed in surface mount conduit? Use raceway that fits 2 to three cables.
13. What color for surface mount conduit? Beige.
ElDorado.pdf |
HughGoodwinMaps.pdf |
NorthwestMaps.pdf |
RettaBrownMap.pdf |
YocumandYocumPrimaryMaps.pdf |
ElDoradoCablingProject.xlsx |
InternalConnectionsTemplateV1513234.xlsm |
OLDRFPForCablingColorsONLY.docx |
Answer:
Flip phones- 10
2 groups of 5 with 2,100 minutes for each group
Total minutes of 4,200.
No data or texting
Answer:
There was no RFI put out during the walk through. All parties present were told that the only document given them was purely for information about parts and what things go together and cabling colors - and nothing else. Each school is a separate bid.
We were careful to expressly state that the information for those kind of things would be on the website and that the website superseded all other information(in addition to specific installation information gained in the walk through by the bidders first hand observations).
Answer:
There was no RFI put out during the walk through. All parties present were told that the only document given them was purely for information about parts and what things go together and nothing else. Each building is a separate bid.
Whenever the work is started it cannot be done during school hours and must be completed by the end of June in order for the school computers to be reconnected and the network made ready for use by school startup.
Answer:
No
Answer:
Copies of the Visio Drawings that exist were given to to all attendies and are posted on the IFCB
Answer:
Any warranties that you bid will need to be excluded from the template and submitted as line item pricing on a separate quote for each school. Parts are all exactly the same so they would have the same warranty. An installation warranty from the installer is desired for the period of two years after completion.
Answer:
Yes, we would like for you to bid that way