Answer:
AISD currently uses Meru Wireless equipment, but there is a possibility of a move to Cisco Wireless equipment
Answer:
No need to call before hand – please arrive at 9am on either day. Install/config charges should be listed on the same template as the equipment (by each school). We also encourage you to submit a bid in your normal format (you can combine all of your documents to one .zip folder to upload) Below are the 10/100 switches in use, the suggested replacement switch model (bids for functional equivalents will be accepted), and the SFPs required for each:
AG-SW1 WS-C2960X-48FPS-L NO SFP required
Fieldhouse-SW1 WS-C2960X-48FPS-L (1) Copper SFP required
Gym-SW1 WS-C2960X-48FPS-L NO SFP required
HS-107A-SW1 WS-C2960X-48FPD-L NO SFP required
HS-107A-SW2 WS-C2960X-48FPS-L NO SFP required
HS-119-SW1 WS-C2960X-48FPD-L (2) Copper SFP required
HS-119-SW2 WS-C2960X-48FPS-L NO SFP required
HS-119-SW3 WS-C2960X-48FPS-L NO SFP required
HS-Gym-FH-SW1 WS-C2960CX-8PC-L NO SFP required
PracticeGym-SW1 WS-C2960CX-8PC-L NO SFP required
All switches are Layer 2 and provide full PoE
Answer:
Yes we will need new cable drops for additional APs. We will not place APs ourselves.
Answer:
Yes we will need new cable drops for additional APs. We will not place APs ourselves. I am certain that we will have room in our racks for all switch placements. We do want the company who gets the job to mount the switches in those racks.
Answer:
We prefer new equipment but we are willing to look at any cost effective solution that fits within the specifications of what we have bid out.